試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A Team member was recently promoted as project manager and has been assigned a $2million. The department manager schedules a meeting to review the project charter within two weeks.What should the project manager do next?
A、Create the project scope statement.
B、Meet with the sponsor to define the business needs.
C、Schedule a kick-off meeting with team members.
D、Review the project management plans with the stakeholders.