試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the planning phase of a project, the project manager realized that there are differences on the understanding of the project deliverables with a project stakeholder,which results in a strained relationship with that stakeholder. What should the project manager do to address this issue?
A、Ignore the stakeholder
B、Arrange a session with the stakeholder to understand the reasons behind the differences and address them
C、Escalate it to the sponsor so that they can sort it out for the project manager
D、Ask the other team members to convince the stakeholder to back down